Scope of Work
Urban planning, Road design, Architectural & Structural design, electro-mechanical design, tender document & execution drawing preparation, and construction supervision.
Project Description
This multi-phased project includes a river barge grain handling and storage facility.
The 89500 m2 land (89 hectare) is located 2 km south of Alexandria port connected directly to the port by River Transport canal. The project includes construction of 120 meter long Quay to be extended to 320 meter in future.
First phase included 17 large grain silos, three bucket elevators, unloading Quay crane , bulk out loading for trucks .(6 lanes) including weighing ,cleaning and automation systems. First phase accommodates 190 000 ton storage and expected annual throughoutput is 2.1 million ton of wheat ,corn and soya beans . Second phase include 3 plat storages for soya meal crushing process for soya beans and truck parking zone with all necessary infrastructure and service buildings
Future total through output is expected to reach 5 million ton by 2020. General planning consultant , terminal planning , cost study, storage structural studies, river port Quay studies.